Village Accepted Amount ACME Assess the water distribution system and upgrade waterlines. $150,000 ALIX Prepare a wastewater lagoon assessment study. $125,000 Rehabilitate a portion of a wastewater main along Main Street. $35,000 Replace a portion of water main along 53 Street and install $219,000 hydrants. AMISK Purchase a lawn mower. $25,000 Develop a water source to supply the water treatment plant. $65,000 ARROWWOOD Purchase and install water meters. $23,737 BARNWELL Purchase a carbon dioxide feed system for the water treatment $45,000 plant. Pave portions of 8 Avenue and 4 Street West. $149,500 BARONS Purchase a fire truck and expand the fire hall. $75,000 Purchase a boom lift. $30,000 Construct sidewalks. $20,000 Replace breathing apparatus for the fire department. $20,500 BAWLF Rehabilitate wastewater lines. $376,617 Expand the fire hall. $93,400 BERWYN Jointly purchase a fire truck with the Municipal District of Peace. $32,754 BITTERN LAKE Purchase a dump trailer for and install a motorized gate at the $30,000 waste management facility. Replace and upgrade playground equipment. $65,000 Install a wheelchair access ramp at the community hall. $15,000 Extend the waterline to the skating rink. $30,000 Upgrade the community centre kitchen. $28,000 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 25 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report BOYLE Upgrade a wastewater lift station. $63,664 Purchase a sidewalk sweeper and a riding lawn mower. $15,000 Rehabilitate sidewalks. $100,000 Rehabilitate and replace water valves and hydrants. $50,000 Rehabilitate and replace gas lines and meters. $100,000 BRETON Replace a portion of road. $184,725 CARBON Rehabilitate wastewater lines along portions of Essex Street and $114,000 Cardock Avenue. CARMANGAY Replace fire hydrants. $20,000 CAROLINE Purchase a lift station pump and wastewater line camera. $16,895 Rehabilitate sidewalks. $40,225 Upgrade a water treatment plant, including replacement of valves, $61,004 pipes, and rehabilitation of pump motors. Replace the heating, ventilation and air cooling system in the $18,000 administration building. CEREAL Construct landscaping and install a sign at the Cereal Fire Hall. $6,500 Purchase and install community welcome signs. $14,500 Rehabilitate the Cereal Arena ice plant. $14,900 Renovate the C.J. Peacock Centre, including paving the parking $70,000 lot. Construct and pave roads. $80,000 Purchase a garbage truck. $46,000 Rehabilitate the gymnasium floor. $23,500 Replace the roof of the Cereal Prairie Pioneer Museum. $28,500 Rehabilitate the public works shop and storage buildings. $10,000 Replace siding and windows at the pumphouse. $6,950 Rehabilitate the arena and the curling rink. $18,000 CHAMPION Purchase various pieces of maintenance equipment. $33,594 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 26 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report CHAMPION Purchase a tractor with attachments. $42,804 CHAUVIN Rehabilitate sidewalks, curbs, and gutters. $31,000 Install waterlines. $30,000 Pave a portion of 3 Avenue. $125,000 Upgrade a wastewater lift station. $42,000 CLYDE Pave portions of several roads. $247,000 COWLEY Purchase and install water meters. $97,000 Replace waterlines and install shut-off valves. $120,000 Replace a portion of a wastewater line. $260,000 CREMONA Prepare a wastewater lagoon design. $37,500 DELIA Replace wastewater lines, manholes, and service connections $414,674 along Main Street and 1 Street. DEWBERRY Purchase water meters. $6,721 Purchase a garbage truck. $43,606 Purchase a variable frequency drive for the water treatment plant. $10,000 Contribute funding to the Alberta Central East Water Corporation $71,047 for the construction of a regional waterline. DONALDA Resurface portions of Bond Street West and Lee Avenue. $20,000 Rehabilitate the municipal water tower. $82,000 Replace water and wastewater lines between Olson $134,192 Street, Wallace Street East, and Railway Avenue. Contribute funding to the County of Stettler for the purchase of $25,000 a regional fire truck. DONNELLY Rehabilitate a parking lot and several back alleys. $8,000 Purchase a Zamboni and replace an overhead door in the Guy- $35,000 Donnelly Sportex. This report reflects the name and status in effect for each municipality at the time the report was produced. Page 27 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report DONNELLY Construct a wastewater line at the municipal campground. $8,000 Construct a sidewalk and rehabilitate the concrete parking pad at $40,000 the firehall. Replace a portion of a wastewater line along 1 Street. $15,000 Replace a portion of a wastewater line at the municipal $21,000 administration building. DUCHESS Rehabilitate several wastewater lines. $28,909 Replace a garbage truck. $175,000 Replace the storm water drain along 2 Street and replace a portion $221,500 of the road. Replace a portion of Louise Avenue. $86,500 EDGERTON Replace portions of road along 51 Street, 56 Avenue, and 57 $179,817 Avenue. FOREMOST Purchase a backhoe. $10,246 Construct roads, curbs, gutters, water, and wastewater lines to a $289,000 subdivision. GIROUXVILLE Improve 50 Avenue from 51 Street to the village boundary, $204,301 including associated roads, curbs, gutters, sidewalks, landscaping, and storm water lines. GLENDON Resurface Main Street. $162,444 Rehabilitate a lift station, including electrical, mechanical, and $143,750 instrumentation upgrades. Rehabilitate a wastewater lagoon. $133,000 Replace well water pumps. $30,000 HAY LAKES Upgrade the surface drainage system. $213,667 HEISLER Purchase a fire pumper truck. $90,000 HILL SPRING Expand and rehabilitate the community hall. $129,785 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 28 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report HOLDEN Install back-up generators for wastewater lift stations. $80,000 HUGHENDEN Purchase a mower. $10,000 Purchase tractor attachments. $12,000 Construct a public works shop. $200,000 HUSSAR Purchase a lawn mower, water tank, and trailer. $9,600 Upgrade the water distribution system, including replacement of $418,500 waterlines and fire hydrants. HYTHE Replace a portion of a wastewater line. $450,633 INNISFREE Rehabilitate the public works building. $100,000 Purchase a trailer with recycling bins. $30,000 Purchase a heavy-duty truck for hauling equipment. $30,000 Construct a golf course and a driving range. $30,000 Rehabilitate a waterline along a portion of 49 Street and a $82,981 wastewater line along a portion of 51 Street. Purchase a loader with a sweeper attachment. $45,000 KITSCOTY Construct a sidewalk. $31,164 Expand the fire hall. $275,000 Extend water, wastewater, and storm water lines along a portion of $250,000 53 Avenue. Develop a lakeside area into a park. $125,000 LINDEN Construct a retaining wall and upgrade the storm water system $433,224 along 1 Street. LOMOND Replace playground equipment. $80,000 Upgrade the water treatment plant. $378,000 LONGVIEW Upgrade the water treatment plant. $412,500 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 29 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report LOUGHEED Rehabilitate a portion of 52 Street from Railway Avenue to $170,000 Townsend Avenue. Purchase a skid steer. $46,500 MARWAYNE Revitalize the downtown including sidewalks, boulevards, $492,560 roadways, and street lighting. Construct a storm water conduit. $746,000 MINBURN Purchase waste collection bins. $9,504 MORRIN Install water and wastewater lines in a new subdivision. $138,000 MUNSON Construct a public works facility. $133,911 MYRNAM Rehabilitate the waterline and sidewalk on Main Street. $71,250 Purchase maintenance equipment, including a wastewater line $40,000 camera system and a snow blade. Purchase a building for use as a police station. $150,000 NAMPA Rehabilitate and replace portions of several roads and sidewalks. $167,900 NOBLEFORD Construct roads, including water and wastewater lines for an $666,265 industrial subdivision. PARADISE VALLEY Purchase a snow blower and a blade attachment. $11,550 Repave portions of 1 Street and East Street. $16,314 ROSEMARY Rehabilitate a wastewater line on Tulip Street. $43,957 Extend the waterline along Centre Street. $14,000 Pave a portion of Aster Street and Gwen Avenue. $96,720 RYCROFT Purchase a tractor. $41,570 RYLEY Purchase computers. $9,800 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 30 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report RYLEY Replace a grader. $52,000 Replace the heating, ventilation, and air conditioning system in the $50,000 community hall. SPRING LAKE Develop Spring Rose Park, including construction of trails and rest $22,000 areas. Construct a walking trail in the Spring Lake Ranch subdivision. $50,000 Purchase a mower. $20,000 STIRLING Construct a new slope and walking path on the Kipp Coulee berm. $135,000 STROME Construct a storage facility and upgrade the public works yard. $8,288 VETERAN Purchase a lawn mower. $20,742 Replace a fire truck and associated equipment. $64,000 Purchase a street sweeper. $36,500 Install new cabinets, countertops, and backsplash at the $7,000 community hall kitchen. Contribute funding to the Veteran Curling Club for electrical $12,686 system upgrades. WABAMUN Upgrade the Wabamun pier. $110,000 Purchase and install water meter readers. $90,000 WARBURG Purchase a grader. $75,000 Pave a portion of 56 Avenue. $450,000 WARNER Rehabilitate and replace water valves. $530,703 WILLINGDON Replace water valves. $30,000 YOUNGSTOWN Construct a building for the wastewater lift station. $240,000 Replace the ice pad in the arena. $20,000 Expand the Youngstown Municipal Library. $20,000 This report reflects the name and status in effect for each municipality at the time the report was produced. Page 31 Project descriptions and amounts include accepted amendments as of June 19, 2013. MUNICIPAL SUSTAINABILITY INITIATIVE - CAPITAL 2012 Accepted Projects Report YOUNGSTOWN Replace the furnace and air-conditioning units in the $30,000 administration building. Replace the air conditioner in the Youngstown Community Hall. $10,000 Summer Village Accepted Amount